progress of project (2019,September)

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 33.53% 14.77%
2 TIAA MRT Extension Line Project 47.39% 48.89%
3 Taichung Metropolitan Area Elevated Railway Project 98.51% 98.54%
4 Chiayi Urban District Elevated Railway Project 6.80% 6.83%
5 Tainan Urban District Railway Underground Project 45.90% 36.95%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 86.26% 86.21%
7 South-Link Line Railway Electrification Project 80.13% 80.97%
8 Hualien-Taitung Efficiency Improvement Project 100% 100%

 

progress  of  project  Bargraph(2019.09.30)

 

Publisher:Railway Bureau, MOTC