progress of project (2020, Oct)

progress of project

2020/10/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project

19.70%

19.92%

2 TIAA MRT Extension Line Project

55.80%

57.17%

3 Taichung Metropolitan Area Elevated Railway Project 

100%

100%

4 Chiayi Urban District Elevated Railway Project

23.25%

23.35%

5 Tainan Urban District Railway Underground Project

63.97%

49.54%

6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project)

90.35%

90.17%

7 South-Link Line Railway Electrification Project

97.25%

97.23%

8 TRA Fengming Temporary Station Project

30%

30%

9 TRA Pingzhen Temporary Station Project

0%

0%

 