progress of project
2020/10/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project |
19.70% |
19.92% |
2 | TIAA MRT Extension Line Project |
55.80% |
57.17% |
3 | Taichung Metropolitan Area Elevated Railway Project |
100% |
100% |
4 | Chiayi Urban District Elevated Railway Project |
23.25% |
23.35% |
5 | Tainan Urban District Railway Underground Project |
63.97% |
49.54% |
6 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) |
90.35% |
90.17% |
7 | South-Link Line Railway Electrification Project |
97.25% |
97.23% |
8 | TRA Fengming Temporary Station Project |
30% |
30% |
9 | TRA Pingzhen Temporary Station Project |
0% |
0% |