Progress of project (July 2022)

Progress of project

2022/7/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 30.05% 30.05%
2 TIAA MRT Extension Line Project 70.89% 71.89%
3 Chiayi Urban District Elevated Railway Project 45.03% 44.09%
4 Tainan Urban District Railway Underground Project 68.29% 68.05%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 93.49% 93.50%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 56.43% 56.98%
8 TRA Pingzhen Temporary Station Project 31.27% 30.60%
9 Taoyuan Urban District Railway Underground Project 18.56% 18.57%
10 Hualien-Taitung Line Dual-Track Engineering Project 6.18% 6.18%

 

 

Bar-chart of all projects' progress (2022.06.30)

 