Progress of project
2022/7/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 30.05% | 30.05% |
2 | TIAA MRT Extension Line Project | 70.89% | 71.89% |
3 | Chiayi Urban District Elevated Railway Project | 45.03% | 44.09% |
4 | Tainan Urban District Railway Underground Project | 68.29% | 68.05% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 93.49% | 93.50% |
6 | South-Link Line Railway Electrification Project | 99.99% | 99.99% |
7 | TRA Fengming Temporary Station Project | 56.43% | 56.98% |
8 | TRA Pingzhen Temporary Station Project | 31.27% | 30.60% |
9 | Taoyuan Urban District Railway Underground Project | 18.56% | 18.57% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 6.18% | 6.18% |