progress of project
2021/2/28
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 20.79% | 20.90% |
2 | TIAA MRT Extension Line Project | 59.41% | 60.41% |
3 | Taichung Metropolitan Area Elevated Railway Project | 100% | 100% |
4 | Chiayi Urban District Elevated Railway Project | 29.50% | 29.55% |
5 | Tainan Urban District Railway Underground Project | 50.90% |
50.90% |
6 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 90.59% | 90.59% |
7 | South-Link Line Railway Electrification Project | 98.55% | 98.55% |
8 | TRA Fengming Temporary Station Project | 30.42% | 30.42% |
9 | TRA Pingzhen Temporary Station Project | 5.70% | 5.70% |