progress of project
2021/3/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 21.04% | 21.13% |
2 | TIAA MRT Extension Line Project | 60.14% | 61.13% |
3 | Taichung Metropolitan Area Elevated Railway Project | 100% | 100% |
4 | Chiayi Urban District Elevated Railway Project | 30.13% | 30.18% |
5 | Tainan Urban District Railway Underground Project | 51.36% |
51.36% |
6 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 90.69% | 90.69% |
7 | South-Link Line Railway Electrification Project | 98.68% | 98.68% |
8 | TRA Fengming Temporary Station Project | 30.91% | 32.38% |
9 | TRA Pingzhen Temporary Station Project | 9.38% | 9.38% |
10 | Taoyuan Urban District Railway Underground Project | 1.09% | 1.09% |