progress of project (April 2022)

progress of project

2022/4/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 26.94% 27.22%
2 TIAA MRT Extension Line Project 68.96% 70.03%
3 Chiayi Urban District Elevated Railway Project 42.72% 42.34%
4 Tainan Urban District Railway Underground Project 64.56% 64.27%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 92.97% 92.98%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 50.45% 51.38%
8 TRA Pingzhen Temporary Station Project 27.65% 27.73%
9 Taoyuan Urban District Railway Underground Project 16.46% 16.47%
10 Hualien-Taitung Line Dual-Track Engineering Project 4.32% 4.32%

 

 

Bar-chart of all projects' progress (2022.04.30)