progress of project (February 2022)

progress of project

2022/2/28

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 25.64% 26.22%
2 TIAA MRT Extension Line Project 67.75% 68.88%
3 Chiayi Urban District Elevated Railway Project 41.21% 40.57%
4 Tainan Urban District Railway Underground Project 62.09% 61.91%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 92.58% 92.58%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 46.46% 47.55%
8 TRA Pingzhen Temporary Station Project 26.45% 26.51%
9 Taoyuan Urban District Railway Underground Project 14.06% 14.08%
10 Hualien-Taitung Line Dual-Track Engineering Project 3.08% 3.08%

 

 