progress of project
2022/2/28
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 25.64% | 26.22% |
2 | TIAA MRT Extension Line Project | 67.75% | 68.88% |
3 | Chiayi Urban District Elevated Railway Project | 41.21% | 40.57% |
4 | Tainan Urban District Railway Underground Project | 62.09% | 61.91% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 92.58% | 92.58% |
6 | South-Link Line Railway Electrification Project | 99.99% | 99.99% |
7 | TRA Fengming Temporary Station Project | 46.46% | 47.55% |