progress of project
2022/3/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 25.90% | 26.64% |
2 | TIAA MRT Extension Line Project | 68.34% | 69.47% |
3 | Chiayi Urban District Elevated Railway Project | 41.96% | 41.43% |
4 | Tainan Urban District Railway Underground Project | 63.35% | 63.08% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 92.80% | 92.80% |
6 | South-Link Line Railway Electrification Project | 100% | 100% |
7 | TRA Fengming Temporary Station Project | 48.45% | 49.44% |
8 | TRA Pingzhen Temporary Station Project | 26.98% | 27.03% |
9 | Taoyuan Urban District Railway Underground Project | 15.26% | 15.27% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 3.70% | 3.70% |