progress of project (March 2022)

progress of project

2022/3/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 25.90% 26.64%
2 TIAA MRT Extension Line Project 68.34% 69.47%
3 Chiayi Urban District Elevated Railway Project 41.96% 41.43%
4 Tainan Urban District Railway Underground Project 63.35% 63.08%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 92.80% 92.80%
6 South-Link Line Railway Electrification Project 100% 100%
7 TRA Fengming Temporary Station Project 48.45% 49.44%
8 TRA Pingzhen Temporary Station Project 26.98% 27.03%
9 Taoyuan Urban District Railway Underground Project 15.26% 15.27%
10 Hualien-Taitung Line Dual-Track Engineering Project 3.70% 3.70%

 

 

progress of project (March 2022)