News

progress of project (May 2022)

progress of project

2022/5/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 27.78% 27.81%
2 TIAA MRT Extension Line Project 69.57% 70.67%
3 Chiayi Urban District Elevated Railway Project 43.36% 42.93%
4 Tainan Urban District Railway Underground Project 65.71% 65.46%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 93.15% 93.17%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 52.44% 53.21%
8 TRA Pingzhen Temporary Station Project 28.73% 28.30%
9 Taoyuan Urban District Railway Underground Project 17.68% 17.68%
10 Hualien-Taitung Line Dual-Track Engineering Project 4.94% 4.94%

 

 

Bar-chart of all projects' progress (2022.04.30)