progress of project
2022/5/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 27.78% | 27.81% |
2 | TIAA MRT Extension Line Project | 69.57% | 70.67% |
3 | Chiayi Urban District Elevated Railway Project | 43.36% | 42.93% |
4 | Tainan Urban District Railway Underground Project | 65.71% | 65.46% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 93.15% | 93.17% |
6 | South-Link Line Railway Electrification Project | 99.99% | 99.99% |
7 | TRA Fengming Temporary Station Project | 52.44% | 53.21% |