Current Progress
42.53%
Current Progress
42.53%
Actual Progress :42.53%,Scheduled Progress:42.53%
Total Construction Contracts:17
The design of this project began in April 110, and some sections are still under design.
The Comprehensive Planning Report was approved by the Executive Yuan on April 8, 2021.
In response to th e increasing tran sportation deman d in the future, to strengthen the transportation capacity of Huadong Railway, and to ta ke en vironmental sustainability and tourism development into account, so as to maintain the unique lifestyle and tourism characteristics of the Huadong area, it is hoped that railway construction will be the main axis of public transportation in the Huadong area. Therefore, th e doubletrack electrificati on plan will be implemented.