Current Progress
74.07%
The project revision plan currently being processed.
Current Progress
74.07%
Actual Progress :74.07%,Scheduled Progress:80.16%
Total Construction Contracts:6
The design of this project began in 2017 and has been completed.
The Comprehensive Planning Report was approved by the Executive Yuan on August 7, 2017.
The Airport Terminal 3 Station (A14) is a station that has been approved for the construction of the Airport MRT Project. However, at that time, the construction schedule of Airport Terminal 3 Station is undecided. Only the main structure of the first phase of the station (platform, tunnel and the space above it) has been completed, and it is used as a transit tunnel at this stage. In order to cooperate with the revenue service of Taoyuan Airport Terminal 3, the Railway Bureau handling the follow-up construction of the Airport Terminal 3 Station. Based on the detailed design results of the Terminal 3, including station architecture furbished, water and electricity environmental control, elevators and escalators, new entrances and exits and other structures (employee area, machine room area, ventilation ducts and escape routes, etc.), construction supervision and the design, procurement, construction of core electromechanical systems, automatic fare collection systems, baggage handling systems, and flight information systems.

This project provides seamless and convenient MRT services for airport passengers. Connected with Terminal 1 Station (A12) and Terminal 2 Station (A13), it will provide high-quality transportation services for passengers entering and leaving Taoyuan International Airport, and enhance the competitiveness and image of Taoyuan International Airport.