跳到主要內容
  • :::
  • Back to Home

  • 網站地圖
  • 中

  • A

  • 分享
  • 搜尋

Railway Bureau, MOTC

  • About RB
    • Leader
      • Director General of RB
    • Organization
      • Organization & Functions
      • Policies and Certification
  • Railway Construction
    • Project Management
      • Progress of Projects
    • Railway Infrastructure Development
      • Under Planning
      • Under Construction
      • Major Construction Projects Completed in Recent Years
    • Railway Elevation and Undergrounding Projects
      • Under Planning
      • Under Construction
      • Major Construction Projects Completed in Recent Years
  • Railway Business
    • Operation Supervision
      • Supervision regulations
      • Safety
      • Inspection
    • Railway Industry
      • Industry Policies
      • Action Plan
    • Station Development
      • Taiwan High Speed Rail
      • Taoyuan Airport MRT
      • Sinking Fund
      • Investment Services
  • Publications
    • Laws and Regulations
    • Integrity Platform
      • Launching Ceremony
      • Contact Meeting
:::
:::
Home
Railway Construction
Railway Infrastructure Development
Under Construction
High-Speed Rail Extension to Yilan

  

High-Speed Rail Extension to Yilan Project Planning


4 Phases of Construction
1. Planning (Completed)
2. Design
3. Construction
4. Completion
4. Completion
-
3. Construction
-
2. Design (Completed)
-
1. Planning (Completed)

The Comprehensive Planning Report and the Revised Feasibility Study Report were officially approved by the Executive Yuan on July 28, 2026.

View more>>
Plan Introduction


The origin of the project

The transportation system along the Taipei–Yilan Corridor—including National Highway No. 5, Provincial Highways No. 2 and No. 9, and Taiwan Railways—has long faced demand that exceeds its capacity.In recent years, extreme weather events and earthquakes have also caused repeated disruptions to external transportation serving eastern Taiwan, significantly affecting travel safety and reliability.To address these challenges, there is a clear need to develop a stable and reliable rail system to improve external connectivity for Yilan, Hualien, and Taitung.

Plan outline

  • Project period:From 2026 to 2037.
  • Project Scope:The proposed route extends eastward from Nangang Station, bypasses the Feitsui Reservoir catchment area, and passes through Xizhi, Pingxi, Shuangxi, and Gongliao in New Taipei City, as well as Toucheng and Jiaoxi in Yilan County, terminating at a station located on the southeast side of the Yilan County Government Center. The total length of the line is approximately 60.6 kilometers, with a daily and monthly inspection depot established on the north side of the Lanyang River.
  • Engineering Content:The entire line adopts an electrified system with double tracks, with a total length of approximately 60.6 kilometers. Among them, the existing tail track section surfacing west of Dakeng Creek is 1 kilometer long, and the newly constructed section is approximately 59.6 kilometers long (including 0.94 kilometers of subgrade, 24.78 kilometers of 12 bridges in total, and 33.88 kilometers of 1 cut-and-cover tunnel and 10 mountain tunnels in total). The mountain tunnels adopt a single-bore, double-track configuration, with emergency walkways reserved on both sides.
  • Project budget:NT$352.175 billion
  • Project location:Taipei City, New Taipei City, and Yilan County
  • Project schematic diagram:

(更新)高鐵延伸宜蘭計畫-英文計畫路線示意圖.JPG

Route Map of the Taiwan High Speed Rail Extension to Yilan Project

Expected benefit

  • To relieve long-standing congestion and capacity constraints along the Yilan–Taipei transportation corridor.
  • By enabling convenient transfers at the HSR Yilan Station to Taiwan Railways services to and from Hualien and Taitung, overall service capacity will be enhanced and the resilience of the eastern rail network strengthened.
  • The HSR Yilan Line is a key project supporting the vision of a high-efficiency, round-island railway network that connects Taiwan within four 90-minute travel zones. It is also an important infrastructure initiative under the government’s Balanced Taiwan policy.

Thank you for using this service. Your satisfaction is our motivation. We welcome you to fill out the satisfaction feedback form for the presentation of this webpage. Your valuable feedback will help us improve our service quality.
*How many points do you give to the presentation of this webpage?
Please click the stars above to provide a rating

If you have any suggestions or areas that need improvement for TRA services, please leave a message at the "Director's Mailbox (opens new window)", and we will handle it carefully as soon as possible.
verification code  
  
:::
  • About RB
    • Leader
    • Organization
  • Railway Construction
    • Project Management
    • Railway Infrastructure Development
    • Railway Elevation and Undergrounding Projects
  • Railway Business
    • Operation Supervision
    • Railway Industry
    • Station Development
  • Publications
    • Laws and Regulations
    • Integrity Platform
  • Privacy Policy  |
  • Information Security Policy  |
  • Open Announcement
  • Today's visits: 0
  • Total visits: 0
Web Accessibility AA Conformance

Emergency Contact: During Office Hours: (02)8072-3333 | After Hours or Holidays: (02)8969-1601 Railway Bureau, MOTC All Rights Reserved | Tel: (02)8072-3333 | Fax: (02)8969-1600 Address: 9F., No.7, Sec. 2, Xianmin Blvd., Banqiao Dist., New Taipei City 220231, Taiwan (R.O.C.)

Ethics Hotline: (02)8969-1540 | Ethics Fax: (02)8969-1539 | Ethics Mailbox: New Taipei City Government Post Office Box 18

Ethics Email: invx@rb.gov.tw Recommended browsers: Chrome, Edge, Safari, Firefox. Screen resolution: 1280 X 810 or higher.


Search
Facebook
YouTube
  • Facebook
  • YouTube