Current Progress
84.78%
4. Completion
-
Current Progress
84.78%
Actual Progress :84.78%,Scheduled Progress:84.56%
Total Construction Contracts:17
Design completed.
The Comprehensive Planning Report was approved by the Executive Yuan on September 9, 2009.
The Tainan Project involves the construction of an 8.23-kilometer-long underground rail line from the south end of the Zhonghua Land Bridge (Yongkang Bridge) to the south end of Shengchan Road. The old Tainan Station building was preserved as a historic site. The new Tainan Station was established along with two new commuter stations—Linsen and South Tainan. The project eliminates nine railway crossings and four underpasses.