Current Progress
85.65%
4. Completion
-
Current Progress
85.65%
Actual Progress :85.65%,Scheduled Progress:85.43%
Total Construction Contracts:17
Design completed.
The Comprehensive Planning Report was approved by the Executive Yuan on September 9, 2009.
The Tainan Project involves the construction of an 8.23-kilometer-long underground rail line from the south end of the Zhonghua Land Bridge (Yongkang Bridge) to the south end of Shengchan Road. The old Tainan Station building was preserved as a historic site. The new Tainan Station was established along with two new commuter stations—Linsen and South Tainan. The project eliminates nine railway crossings and four underpasses.

Route Map of the Tainan Urban District Railway Underground Project