Project Management

Progress of project

Progress of project

2022/8/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 32.37% 32.40%
2 TIAA MRT Extension Line Project 71.60% 72.63%
3 Chiayi Urban District Elevated Railway Project 45.63% 44.68%
4 Tainan Urban District Railway Underground Project 69.67% 69.42%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 93.67% 93.69%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 58.43% 59.92%
8 TRA Pingzhen Temporary Station Project 32.67% 30.81%
9 Taoyuan Urban District Railway Underground Project 19.13% 19.13%
10 Hualien-Taitung Line Dual-Track Engineering Project 6.80% 6.80%

 

 

Bar-chart of all projects' progress (2022.08.31)