Progress of Projects
2025/3/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 66.00% | 65.30% |
2 | TIAA MRT Extension Line Project | 84.24% | 84.59% |
3 | Chiayi Urban District Elevated Railway Project | 49.43% | 49.44% |
4 | Tainan Urban District Railway Underground Project | 92.45% | 90.03% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 99.20% | 99.20% |
6 | TRA Pingzhen Temporary Station Project | 69.970% | 71.20% |
7 | Taoyuan Urban District Railway Underground Project | 42.67% | 32.52% |
8 | Hualien-Taitung Line Dual-Track Engineering Project | 43.58% | 31.41% |