Project Management

Progress of Projects (February 2024)

Progress of Projects

2024/03/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 68.33% 62.34%
2 TIAA MRT Extension Line Project 79.85% 80.52%
3 Chiayi Urban District Elevated Railway Project 69.86% 58.90%
4 Tainan Urban District Railway Underground Project 88.94% 85.85%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 97.66% 97.69%
6 TRA Fengming Temporary Station Project 94.57% 94.57%
7 TRA Pingzhen Temporary Station Project 52.53% 53.03%
8 Taoyuan Urban District Railway Underground Project 34.50% 30.88%
9 Hualien-Taitung Line Dual-Track Engineering Project 22.23% 17.95%