Project Management

Progress of Projects (August 2024)

Progress of Projects

2024/08/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 61.34% 61.19%
2 TIAA MRT Extension Line Project 81.83% 82.33%
3 Chiayi Urban District Elevated Railway Project 45.39% 45.42%
4 Tainan Urban District Railway Underground Project 90.05% 87.07%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 98.43% 98.45%
6 TRA Fengming Temporary Station Project 98.38% 98.40%
7 TRA Pingzhen Temporary Station Project 56.94% 56.38%
8 Taoyuan Urban District Railway Underground Project 38.24% 31.69%
9 Hualien-Taitung Line Dual-Track Engineering Project 29.22% 22.41%