Progress of Projects (August 2024)
Progress of Projects
2024/08/31
Item |
Project |
Scheduled Progress |
Actual Progress |
1 |
the Additional TIAA MRT Airport Terminal 3 Station (A14) Project |
61.34% |
61.19% |
2 |
TIAA MRT Extension Line Project |
81.83% |
82.33% |
3 |
Chiayi Urban District Elevated Railway Project |
45.39% |
45.42% |
4 |
Tainan Urban District Railway Underground Project |
90.05% |
87.07% |
5 |
Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) |
98.43% |
98.45% |
6 |
TRA Fengming Temporary Station Project |
98.38% |
98.40% |
7 |
TRA Pingzhen Temporary Station Project |
56.94% |
56.38% |
8 |
Taoyuan Urban District Railway Underground Project |
38.24% |
31.69% |
9 |
Hualien-Taitung Line Dual-Track Engineering Project |
29.22% |
22.41% |
Publisher:Railway Bureau, MOTC