 Project Management

progress of project (2019,June)

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 24.03% 14.08%
2 TIAA MRT Extension Line Project 45.86% 46.75%
3 Taichung Metropolitan Area Elevated Railway Project 98.30% 98.27%
4 Chiayi Urban District Elevated Railway Project 4.28% 4.29%
5 Tainan Urban District Railway Underground Project 37.15% 35.55%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 85.71% 85.72%
7 South-Link Line Railway Electrification Project 73.06% 74.36%
8 Hualien-Taitung Efficiency Improvement Project 99.95% 99.95%

 

progress  of  project  Bargraph(2019.06.30)