 Project Management

Progress of project

Progress of project

2022/10/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 35.52% 35.53%
2 TIAA MRT Extension Line Project 72.94% 73.85%
3 Chiayi Urban District Elevated Railway Project 48.07% 47.12%
4 Tainan Urban District Railway Underground Project 72.40% 72.05%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 94.06% 94.07%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 62.42% 63.76%
8 TRA Pingzhen Temporary Station Project 35.76% 33.07%
9 Taoyuan Urban District Railway Underground Project 20.53% 20.49%
10 Hualien-Taitung Line Dual-Track Engineering Project 8.14% 8.14%

 

 

Bar-chart of all projects' progress (2022.10.31)

 