 Project Management

progress of project

progress of project

2020/2/29

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 45.01% 16.32%
2 TIAA MRT Extension Line Project 50.80% 53.27%
3 Taichung Metropolitan Area Elevated Railway Project 99.08% 99.11%
4 Chiayi Urban District Elevated Railway Project 11.50% 11.68%
5 Tainan Urban District Railway Underground Project 51.88% 41.81%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 87.95% 87.85%
7 South-Link Line Railway Electrification Project 89.88% 89.88%
8 Hualien-Taitung Efficiency Improvement Project 100% 100%
9 TRA Fengming Temporary Station Project 0.00% 0.00%

progress 2020.02

 

Publisher:Railway Bureau, MOTC