 Project Management

Progress of Projects (November 2025)

Progress of Projects

2025/11/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 74.10% 72.48%
2 TIAA MRT Extension Line Project 86.21% 86.20%
3 Chiayi Urban District Elevated Railway Project 55.70% 55.71%
4 Tainan Urban District Railway Underground Project 79.06% 79.25%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 99.92% 99.92%
6 TRA Pingzhen Temporary Station Project 92.93% 92.92%
7 Taoyuan Urban District Railway Underground Project 50.82% 34.61%
8 Hualien-Taitung Line Dual-Track Engineering Project 62.95% 48.04%

 