 Project Management

progress of project

progress of project

2020/6/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 55.38% 18.08%
2 TIAA MRT Extension Line Project 52.88% 54.42%
3 Taichung Metropolitan Area Elevated Railway Project 100% 100%
4 Chiayi Urban District Elevated Railway Project 16.60% 17.02%
5 Tainan Urban District Railway Underground Project 58.63% 46.29%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 89.16% 89.02%
7 South-Link Line Railway Electrification Project 94.68% 94.44%
8 Hualien-Taitung Efficiency Improvement Project 100% 100%
9 TRA Fengming Temporary Station Project 15.00% 15.00%