 Project Management

Progress of Projects (July 2025)

Progress of Projects

2025/7/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 68.76% 67.94%
2 TIAA MRT Extension Line Project 85.22% 85.41%
3 Chiayi Urban District Elevated Railway Project 52.56% 52.59%
4 Tainan Urban District Railway Underground Project 75.71% 75.88%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 99.61% 99.61%
6 TRA Pingzhen Temporary Station Project 81.45% 82.13%
7 Taoyuan Urban District Railway Underground Project 44.87% 33.27%
8 Hualien-Taitung Line Dual-Track Engineering Project 53.07% 39.24%

 