 Project Management

progress of project

progress of project

2022/6/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 28.27% 28.16%
2 TIAA MRT Extension Line Project 70.17% 71.29%
3 Chiayi Urban District Elevated Railway Project 44.05% 43.12%
4 Tainan Urban District Railway Underground Project 66.99% 66.75%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 93.32% 93.34%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 54.44% 55.11%
8 TRA Pingzhen Temporary Station Project 29.95% 29.29%
9 Taoyuan Urban District Railway Underground Project 17.99% 17.99%
10 Hualien-Taitung Line Dual-Track Engineering Project 5.56% 5.56%

 

 

Bar-chart of all projects' progress (2022.06.30)

 

Publisher:Railway Bureau, MOTC
Update time: 2022-07-13 11:59:00