Progress of Projects (August 2025)

Progress of Projects

2025/8/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 70.02% 68.78%
2 TIAA MRT Extension Line Project 85.47% 85.60%
3 Chiayi Urban District Elevated Railway Project 53.53% 53.55%
4 Tainan Urban District Railway Underground Project 76.43% 76.61%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 99.70% 99.70%
6 TRA Pingzhen Temporary Station Project 84.32% 84.95%
7 Taoyuan Urban District Railway Underground Project 46.21% 33.71%
8 Hualien-Taitung Line Dual-Track Engineering Project 55.54% 41.38%

 