 Project Management

progress of project

progress of project

2020/9/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 19.43% 19.62%
2 TIAA MRT Extension Line Project 54.73% 56.31%
3 Taichung Metropolitan Area Elevated Railway Project 100% 100%
4 Chiayi Urban District Elevated Railway Project 20.57% 20.66%
5 Tainan Urban District Railway Underground Project 62.73% 49.12%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 90.08% 89.90%
7 South-Link Line Railway Electrification Project 96.71% 96.68%
8 TRA Fengming Temporary Station Project 30% 30%
9 TRA Pingzhen Temporary Station Project 0% 0%