 Project Management

Progress of Projects (October 2025)

Progress of Projects

2025/10/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 71.70% 70.97%
2 TIAA MRT Extension Line Project 85.97% 86.03%
3 Chiayi Urban District Elevated Railway Project 54.91% 54.92%
4 Tainan Urban District Railway Underground Project 78.17% 78.36%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 99.86% 99.86%
6 TRA Pingzhen Temporary Station Project 90.06% 90.06%
7 Taoyuan Urban District Railway Underground Project 49.48% 34.10%
8 Hualien-Taitung Line Dual-Track Engineering Project 60.48% 45.81%

 