 Project Management

progress of project (2019,October)

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 35.95% 15.02%
2 TIAA MRT Extension Line Project 47.85% 49.64%
3 Taichung Metropolitan Area Elevated Railway Project 98.62% 98.63%
4 Chiayi Urban District Elevated Railway Project 7.69% 7.76%
5 Tainan Urban District Railway Underground Project 47.07% 37.77%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 86.48% 86.42%
7 South-Link Line Railway Electrification Project 82.25% 82.97%
8 Hualien-Taitung Efficiency Improvement Project 100% 100%

 

 

progress  of  project  Bargraph(2019.10.31)

Publisher:Railway Bureau, MOTC