 Project Management

Progress of Projects (August 2024)

Progress of Projects

2024/09/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 62.04% 61.88%
2 TIAA MRT Extension Line Project 82.22% 82.69%
3 Chiayi Urban District Elevated Railway Project 45.90% 45.93%
4 Tainan Urban District Railway Underground Project 90.25% 87.78%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 98.56% 98.57%
6 TRA Fengming Temporary Station Project 98.98% 99.00%
7 TRA Pingzhen Temporary Station Project 57.82% 56.98%
8 Taoyuan Urban District Railway Underground Project 38.95% 31.83%
9 Hualien-Taitung Line Dual-Track Engineering Project 31.08% 23.31%

Publisher:Railway Bureau, MOTC