Progress of Projects
2025/7/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 68.76% | 67.94% |
2 | TIAA MRT Extension Line Project | 85.22% | 85.41% |
3 | Chiayi Urban District Elevated Railway Project | 52.56% | 52.59% |
4 | Tainan Urban District Railway Underground Project | 75.71% | 75.88% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 99.61% | 99.61% |
6 | TRA Pingzhen Temporary Station Project | 81.45% | 82.13% |
7 | Taoyuan Urban District Railway Underground Project | 44.87% | 33.27% |
8 | Hualien-Taitung Line Dual-Track Engineering Project | 53.07% | 39.24% |