Progress of Projects
2025/8/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 70.02% | 68.78% |
2 | TIAA MRT Extension Line Project | 85.47% | 85.60% |
3 | Chiayi Urban District Elevated Railway Project | 53.53% | 53.55% |
4 | Tainan Urban District Railway Underground Project | 76.43% | 76.61% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 99.70% | 99.70% |