progress of project (Jan. 2021)

progress of project

2021/1/31     

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project

20.65%

20.69%

2 TIAA MRT Extension Line Project

58.67%

59.72%

3 Taichung Metropolitan Area Elevated Railway Project 

100%

100%

4 Chiayi Urban District Elevated Railway Project

28.39%

28.43%

5 Tainan Urban District Railway Underground Project

50.76%

50.76%

6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project)

90.47%

90.47%

7 South-Link Line Railway Electrification Project

98.42%

98.42%

8 TRA Fengming Temporary Station Project

30.21%

30.32%

9 TRA Pingzhen Temporary Station Project

2.10%

2.10%