progress of project
2021/1/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project |
20.65% |
20.69% |
2 | TIAA MRT Extension Line Project |
58.67% |
59.72% |
3 | Taichung Metropolitan Area Elevated Railway Project |
100% |
100% |
4 | Chiayi Urban District Elevated Railway Project |
28.39% |
28.43% |
5 | Tainan Urban District Railway Underground Project |
50.76% |
50.76% |
6 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) |
90.47% |
90.47% |
7 | South-Link Line Railway Electrification Project |
98.42% |
98.42% |
8 | TRA Fengming Temporary Station Project |
30.21% |
30.32% |
9 | TRA Pingzhen Temporary Station Project |
2.10% |
2.10% |