progress of project (Apr. 2021)

progress of project

2021/4/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 20.21% 20.30%
2 TIAA MRT Extension Line Project 60.87% 61.86%
3 Taichung Metropolitan Area Elevated Railway Project 100% 100%
4 Chiayi Urban District Elevated Railway Project 31.02% 31.06%
5 Tainan Urban District Railway Underground Project 51.66% 51.64%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 90.78% 90.78%
7 South-Link Line Railway Electrification Project 98.81% 98.81%
8 TRA Fengming Temporary Station Project 31.61% 33.05%
9 TRA Pingzhen Temporary Station Project 12.30% 12.30%
10 Taoyuan Urban District Railway Underground Project 1.88% 1.88%
11 Hualien-Taitung Line Dual-Track Engineering Project 3.83% 3.83%

 

progress chart (April 2021)

 

 

Publisher:Railway Bureau, MOTC