progress of project (May 2021)

 

progress of project

2021/5/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 21.53% 21.63%
2 TIAA MRT Extension Line Project 61.61% 62.62%
3 Taichung Metropolitan Area Elevated Railway Project 100% 100%
4 Chiayi Urban District Elevated Railway Project 31.92% 31.84%
5 Tainan Urban District Railway Underground Project 52.50% 52.27%
6 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 90.88% 90.88%
7 South-Link Line Railway Electrification Project 98.96% 98.96%
8 TRA Fengming Temporary Station Project 32.45% 33.89%
9 TRA Pingzhen Temporary Station Project 14.47% 14.47%
10 Taoyuan Urban District Railway Underground Project 2.49% 2.49%
11 Hualien-Taitung Line Dual-Track Engineering Project 4.78% 4.78%

 

 

progress of project (May 2021)

 

 