progress of project
2021/5/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 21.53% | 21.63% |
2 | TIAA MRT Extension Line Project | 61.61% | 62.62% |
3 | Taichung Metropolitan Area Elevated Railway Project | 100% | 100% |
4 | Chiayi Urban District Elevated Railway Project | 31.92% | 31.84% |
5 | Tainan Urban District Railway Underground Project | 52.50% | 52.27% |
6 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 90.88% | 90.88% |
7 | South-Link Line Railway Electrification Project | 98.96% | 98.96% |
8 | TRA Fengming Temporary Station Project | 32.45% | 33.89% |
9 | TRA Pingzhen Temporary Station Project | 14.47% | 14.47% |
10 | Taoyuan Urban District Railway Underground Project | 2.49% | 2.49% |
11 | Hualien-Taitung Line Dual-Track Engineering Project | 4.78% | 4.78% |