progress of project
2021/6/30
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 21.89% | 22.00% |
2 | TIAA MRT Extension Line Project | 62.34% | 63.33% |
3 | Chiayi Urban District Elevated Railway Project | 33.06% | 33.09% |
4 | Tainan Urban District Railway Underground Project | 53.48% | 52.78% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 90.99% | 90.99% |
6 | South-Link Line Railway Electrification Project | 99.09% | 99.09% |
7 | TRA Fengming Temporary Station Project | 33.57% | 35.02% |
8 | TRA Pingzhen Temporary Station Project | 16.87% | 16.87% |
9 | Taoyuan Urban District Railway Underground Project | 3.67% | 3.67% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 5.72% | 5.72% |