progress of project (June 2021)

progress of project

2021/6/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 21.89% 22.00%
2 TIAA MRT Extension Line Project 62.34% 63.33%
3 Chiayi Urban District Elevated Railway Project 33.06% 33.09%
4 Tainan Urban District Railway Underground Project 53.48% 52.78%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 90.99% 90.99%
6 South-Link Line Railway Electrification Project 99.09% 99.09%
7 TRA Fengming Temporary Station Project 33.57% 35.02%
8 TRA Pingzhen Temporary Station Project 16.87% 16.87%
9 Taoyuan Urban District Railway Underground Project 3.67% 3.67%
10 Hualien-Taitung Line Dual-Track Engineering Project 5.72% 5.72%

 

 

progress of project (June 2021)

 

 

Publisher:Railway Bureau, MOTC
Update time: 2022-05-12 11:41:00