progress of project
2021/8/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 22.34% | 22.40% |
2 | TIAA MRT Extension Line Project | 63.07% | 64.04% |
3 | Chiayi Urban District Elevated Railway Project | 33.92% | 33.94% |
4 | Tainan Urban District Railway Underground Project | 54.41% | 53.64% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 91.11% | 91.11% |
6 | South-Link Line Railway Electrification Project | 99.21% | 99.21% |
7 | TRA Fengming Temporary Station Project | 34.76% | 35.77% |
8 | TRA Pingzhen Temporary Station Project | 19.27% | 19.27% |
9 | Taoyuan Urban District Railway Underground Project | 4.81% | 4.81% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 0.72% | 1.06% |