 News

progress of project (July 2021)

progress of project

2021/8/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 22.34% 22.40%
2 TIAA MRT Extension Line Project 63.07% 64.04%
3 Chiayi Urban District Elevated Railway Project 33.92% 33.94%
4 Tainan Urban District Railway Underground Project 54.41% 53.64%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 91.11% 91.11%
6 South-Link Line Railway Electrification Project 99.21% 99.21%
7 TRA Fengming Temporary Station Project 34.76% 35.77%
8 TRA Pingzhen Temporary Station Project 19.27% 19.27%
9 Taoyuan Urban District Railway Underground Project 4.81% 4.81%
10 Hualien-Taitung Line Dual-Track Engineering Project 0.72% 1.06%

 

progress of project (July 2021)

 

 