progress of project (August 2021)

progress of project

2021/8/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 22.76% 22.83%
2 TIAA MRT Extension Line Project 63.80% 64.74%
3 Chiayi Urban District Elevated Railway Project 34.84% 34.87%
4 Tainan Urban District Railway Underground Project 55.39% 54.66%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 91.23% 91.23%
6 South-Link Line Railway Electrification Project 99.35% 99.35%
7 TRA Fengming Temporary Station Project 36.02% 37.31%
8 TRA Pingzhen Temporary Station Project 20.92% 20.92%
9 Taoyuan Urban District Railway Underground Project 5.96% 5.96%
10 Hualien-Taitung Line Dual-Track Engineering Project 0.96% 1.06%

 

progress of project (August 2021)

 