progress of project
2021/8/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 22.76% | 22.83% |
2 | TIAA MRT Extension Line Project | 63.80% | 64.74% |
3 | Chiayi Urban District Elevated Railway Project | 34.84% | 34.87% |
4 | Tainan Urban District Railway Underground Project | 55.39% | 54.66% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 91.23% | 91.23% |
6 | South-Link Line Railway Electrification Project | 99.35% | 99.35% |
7 | TRA Fengming Temporary Station Project | 36.02% | 37.31% |
8 | TRA Pingzhen Temporary Station Project | 20.92% | 20.92% |
9 | Taoyuan Urban District Railway Underground Project | 5.96% | 5.96% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 0.96% | 1.06% |