progress of project (September 2021)

progress of project

2021/9/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 23.29% 23.34%
2 TIAA MRT Extension Line Project 64.53% 65.38%
3 Chiayi Urban District Elevated Railway Project 35.78% 35.80%
4 Tainan Urban District Railway Underground Project 56.27% 55.58%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 91.37% 91.37%
6 South-Link Line Railway Electrification Project 99.49% 99.49%
7 TRA Fengming Temporary Station Project 37.35% 38.23%
8 TRA Pingzhen Temporary Station Project 21.97% 21.97%
9 Taoyuan Urban District Railway Underground Project 7.39% 7.39%
10 Hualien-Taitung Line Dual-Track Engineering Project 1.20% 1.20%

 

 