progress of project
2021/9/30
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 23.29% | 23.34% |
2 | TIAA MRT Extension Line Project | 64.53% | 65.38% |
3 | Chiayi Urban District Elevated Railway Project | 35.78% | 35.80% |
4 | Tainan Urban District Railway Underground Project | 56.27% | 55.58% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 91.37% | 91.37% |
6 | South-Link Line Railway Electrification Project | 99.49% | 99.49% |
7 | TRA Fengming Temporary Station Project | 37.35% | 38.23% |
8 | TRA Pingzhen Temporary Station Project | 21.97% | 21.97% |
9 | Taoyuan Urban District Railway Underground Project | 7.39% | 7.39% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 1.20% | 1.20% |