progress of project (October 2021)

progress of project

2021/10/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 24.00% 24.02%
2 TIAA MRT Extension Line Project 65.27% 66.04%
3 Chiayi Urban District Elevated Railway Project 36.88% 36.90%
4 Tainan Urban District Railway Underground Project 57.30% 56.87%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 91.50% 91.50%
6 South-Link Line Railway Electrification Project 99.64% 99.64%
7 TRA Fengming Temporary Station Project 38.82% 39.94%
8 TRA Pingzhen Temporary Station Project 23.02% 23.02%
9 Taoyuan Urban District Railway Underground Project 8.77% 8.77%
10 Hualien-Taitung Line Dual-Track Engineering Project 1.44% 1.44%

 

 

progress of project (October 2021)

 