progress of project
2021/10/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 24.00% | 24.02% |
2 | TIAA MRT Extension Line Project | 65.27% | 66.04% |
3 | Chiayi Urban District Elevated Railway Project | 36.88% | 36.90% |
4 | Tainan Urban District Railway Underground Project | 57.30% | 56.87% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 91.50% | 91.50% |
6 | South-Link Line Railway Electrification Project | 99.64% | 99.64% |
7 | TRA Fengming Temporary Station Project | 38.82% | 39.94% |
8 | TRA Pingzhen Temporary Station Project | 23.02% | 23.02% |
9 | Taoyuan Urban District Railway Underground Project | 8.77% | 8.77% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 1.44% | 1.44% |