progress of project

2021/11/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 24.66% 24.72%
2 TIAA MRT Extension Line Project 66.00% 66.73%
3 Chiayi Urban District Elevated Railway Project 38.16% 37.97%
4 Tainan Urban District Railway Underground Project 58.39% 58.02%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 91.66% 91.66%
6 South-Link Line Railway Electrification Project 99.80% 99.80%
7 TRA Fengming Temporary Station Project 40.36% 42.08%
8 TRA Pingzhen Temporary Station Project 24.22% 24.22%
9 Taoyuan Urban District Railway Underground Project 10.15% 10.15%
10 Hualien-Taitung Line Dual-Track Engineering Project 1.68% 1.68%

 

 

progress of project (November 2021)

 