progress of project
2021/12/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 25.30% | 25.33% |
2 | TIAA MRT Extension Line Project | 66.74% | 67.05% |
3 | Chiayi Urban District Elevated Railway Project | 39.70% | 39.51% |
4 | Tainan Urban District Railway Underground Project | 59.57% | 59.40% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 91.82% | 91.82% |
6 | South-Link Line Railway Electrification Project | 99.98% | 99.98% |
7 | TRA Fengming Temporary Station Project | 41.97% | 43.31% |
8 | TRA Pingzhen Temporary Station Project | 25.45% | 25.48% |
9 | Taoyuan Urban District Railway Underground Project | 11.68% | 11.70% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 1.92% | 1.92% |