progress of project
2022/1/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 25.45% | 25.78% |
2 | TIAA MRT Extension Line Project | 67.24% | 68.03% |
3 | Chiayi Urban District Elevated Railway Project | 40.63% | 40.15% |
4 | Tainan Urban District Railway Underground Project | 61.05% | 60.88% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 92.36% | 92.36% |
6 | South-Link Line Railway Electrification Project | 99.99% | 99.99% |
7 | TRA Fengming Temporary Station Project | 44.46% | 45.69% |
8 | TRA Pingzhen Temporary Station Project | 25.94% | 26.00% |
9 | Taoyuan Urban District Railway Underground Project | 12.87% | 12.89% |
10 | Hualien-Taitung Line Dual-Track Engineering Project | 2.46% | 2.46% |