progress of project (January 2022)

progress of project

2022/1/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 25.45% 25.78%
2 TIAA MRT Extension Line Project 67.24% 68.03%
3 Chiayi Urban District Elevated Railway Project 40.63% 40.15%
4 Tainan Urban District Railway Underground Project 61.05% 60.88%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 92.36% 92.36%
6 South-Link Line Railway Electrification Project 99.99% 99.99%
7 TRA Fengming Temporary Station Project 44.46% 45.69%
8 TRA Pingzhen Temporary Station Project 25.94% 26.00%
9 Taoyuan Urban District Railway Underground Project 12.87% 12.89%
10 Hualien-Taitung Line Dual-Track Engineering Project 2.46% 2.46%

 

 